Decision details

Dunnings Bridge Road Corridor Public Realm Improvements

Decision Maker: Cabinet Member - Technical Services (meeting)

Decision status: Recommendations approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

Further to Minute No. 143 of the meeting of the Cabinet Member - Technical Services held on 24 February 2010, the Cabinet considered the report of the Strategic Director - Communities which provided details of the proposed project to undertake public realm improvements to the Dunnings Bridge Road Corridor, Bootle and sought approval to the inclusion of the scheme within the Capital Programme for 2010/11.

 

This was a Key Decision and was included on the Council's Forward Plan of Key Decisions.

 

RESOLVED:   That

 

(1)            approval be given to the inclusion of the Dunnings Bridge Road Corridor Project within the Capital Programme 2010/11 subject to the funding from the European Regional Development Fund, Regional Development Agency and Local Transport Plan being confirmed;

 

(2)       it be noted that no further expenditure commitment will be entered into until all resources for the project are secured; and

 

(3)       further progress reports on the project be submitted to the Cabinet.

Report author: Alan Moore

Publication date: 09/03/2010

Date of decision: 04/03/2010

Decided at meeting: 04/03/2010 - Cabinet

Effective from: 17/03/2010

Accompanying Documents: