Decision Maker: Cabinet Sub-Committee - Capital Programme, Cabinet
Decision status: Recommendations approved
Is Key decision?: No
Is subject to call in?: No
Further to Minute No. 68 of the Cabinet Meeting held on 8 December 2011,
the Sub Committee considered the joint report of the Strategic Director - Place
and the Head of Corporate Finance and ICT which provided an update on the
committed and uncommitted schemes in the Capital Programme.
RESOLVED:
That the Cabinet be requested to recommend that the Council give approval
to:
(i) the confirmation of the following uncommitted capital schemes in the
Capital Programme:
· Other Capital Maintenance - £1,089k
· Other Modernisation £88k
· Other Schools Access Initiative £102k
· New Pupil Places - £508k
· Disabled Facilities - £26k
· IT Server Replacement - £25k
· Members ICT - £27k
· Adult Personal Social Services - £1,605k
· Hesketh Park Visitor Office - £50k
· Southport Sports Park £75k
· Botanic Gardens Museum and Roof - £25k
· Southport Commerce Park - £884k
(ii) the reduction/abandonment of the following uncommitted schemes to the Capital Programme:
· South Sefton 6th Form Centre £70k
· Waste Infrastructure Grant - £244k
· Development Fund - £9k
· Members ICT - £50k
· IT Server Replacement - £23k
· Southport Sports Park - £307k
· Highway Parking Improvements - £100k; and
(iii) the merging of the IT Server Replacement and Botanic Gardens Museum and Roof schemes to form a Capital Contingency Fund.
Publication date: 19/12/2011
Date of decision: 15/12/2011
Decided at meeting: 15/12/2011 - Cabinet Sub-Committee - Capital Programme