Issue - meetings

Refurbishment of Aintree Davenhill Primary School

Meeting: 04/02/2010 - Cabinet (Item 279)

279 Davenhill Primary School, Aintree - Proposed Extensions and Alterations pdf icon PDF 73 KB

Report of the Strategic Director - Communities

Minutes:

The Cabinet considered the report of the Strategic Director - Communities on the tenders received for the provision of extensions and alterations to the accommodation at Davenhill Primary School, Aintree.

 

This was a Key Decision and was included in the Council's Forward Plan of Key Decisions.

 

RESOLVED:   That

 

(1)            approval be given to the allocation of £2,488.647 in the Children's Services Capital programme for this scheme, funded from the Primary Capital budget (£2,000,000);  Modernisation Programme (£398,647) and the schools Devolved Formula Capital funding (£90,000);

 

(2)       the lowest tender submitted by Lockwoods Construction (Liverpool) Ltd of Bootle in the sum of £1,988,385 be accepted; and

 

(3)       the Legal and Democratic Services Director be requested to enter into a formal contract with the successful tenderer.