The Cabinet considered the report of the
Executive Director - Corporate Resources and Customer Services that
advised of:
(1)
|
the current estimated financial impact of
COVID-19 on the 2020/21 Budget;
|
(2)
|
the current forecast revenue outturn position
for the Council for 2020/21;
|
(3)
|
the current forecast on Council Tax and
Business Rates collection for 2020/21; and
|
(4)
|
the monitoring position of the Council’s
capital programme to the end of June 2020 relating to:
·
the forecast expenditure to year end;
·
variations against the approved budgets and an explanation of those
variations for consideration by Members;
·
updates to spending profiles and proposed amendments to capital
budgets necessary to ensure the efficient delivery of capital
projects are also presented for approval.
|
Stephan Van Arendsen, Executive Director -
Corporate Resources and Customer Services verbally updated the
Cabinet in respect of the offer of a £1m grant to support
projects in Southport. Mr. Van Arendsen advised that the Southport
Town Board had informed the Council that they would like to
progress 2 schemes to utilise the funding, namely Southport Market
Hall and a Street Lighting project. On
receipt of appropriate minutes from the Board Mr. Van Arendsen, the
Council’s s151 officer would inform MHCLG of this decision
and the schemes would progress through the Council’s
established governance processes.
Decision Made:
That:
(A)
|
in respect of the Revenue Budget:
(1)
|
the current estimated impact of
COVID-19 on the 2020/21 Budget together with the key issues that
will influence the final position; and that further government
guidance is awaited on the additional support that will be provided
to the Council which will inform the Council’s strategy for
delivering financial sustainability be noted;
|
(2)
|
the financial risks associated
with the delivery of the 2020/21 revenue budget and the material
variations that are to be expected to the current estimates
contained in the report be recognised, and it be agreed that
subsequent reports provide updates and where appropriate remedial
action plans as appropriate;
|
(3)
|
Authority be granted to the
Leader of the Council to approve any further expenditure from the
Emergency Fund following advice from the Chief Executive and s151
officer with any decisions being reported to future Cabinet
meetings;
|
(4)
|
the government grant funding
that has been received and that has been used to support the
response to the pandemic and which has been distributed in
accordance with central government guidance be noted;
|
(5)
|
the current forecast revenue
outturn position for 2020/21 be noted;
|
(6)
|
the implementation of a
remedial action plan to partially mitigate the forecast outturn
position, and the principles to be adopted to meet the remaining
forecast deficit be approved;
|
(7)
|
the temporary additional
resources required as part of the demand management programme in
respect of fostering, family finder and direct payments be approved
and that this provision be reviewed at the end of Q1 in 2021/22 to
confirm that the savings identified are being delivered;
and
|
(8)
|
It be acknowledged that the forecast outturn
position will continue to be reviewed to ensure a balanced forecast
outturn position and financial sustainability can be achieved;
and
|
|
(B)
|
in respect of the Capital Budget:
(1)
|
the spending profiles across financial years
for the approved Capital Programme (paragraph 7.1 of the report) be
noted;
|
(2)
|
the proposed updates to the School’s
Programme (paragraph 7.2 of the report) be approved;
|
(3)
|
Council be recommended to approve the revised
Transport Allocations as shown in paragraph 7.3 of the report;
|
(4)
|
the latest capital expenditure position as at
30 June 2020 of £2.423m (paragraph 7.4.2 of the report) with
the latest full year forecast of £35.825m (paragraph 7.5.1 of
the report) be noted;
|
(5)
|
the explanations of variances to project
budgets (paragraph 7.5.2 of the report) be noted;
|
(6)
|
It be noted that capital resources will be
managed by the Executive Director - Corporate Resources and
Customer Services to ensure the capital programme remains fully
funded and that capital funding arrangements secure the maximum
financial benefit to the Council (paragraph 7.6 of the report);
and
|
(7)
|
in order to comply with the guidance set out
by Ministry of Housing, Communities and Local Government (MHCLG) in
respect of the offer from central government of £1m to
Southport as part of the Towns Fund, it be approved that the
Southport Towns Fund Board will advise the Council of the
project(s) that it is recommending and will be completed with the
grant allocation and that this will be communicated to MHCLG via
the Councils s151 officer as per the guidance; and following approval this will be the subject of a
recommendation to Members in accordance with the Council’s
Financial Procedure Rules (paragraph 7.7 of the report).
|
|
Reasons for
Decision:
To ensure Cabinet are informed of the forecast
outturn position for the 2020/21 Revenue Budget as at the end of
June 2020, including delivery of a remedial action plan, and to
provide an updated forecast of the outturn position regarding the
collection of Council Tax and Business Rates.
To keep Members informed of the progress of
the Capital Programme against the profiled budget for 2019/20 and
agreed allocations for future years.
To progress any changes that are required in
order to maintain a relevant and accurate budget profile necessary
for effective monitoring of the Capital Programme.
To approve any updates to funding resources so
that they can be applied to capital schemes in the delivery of the
Council’s overall capital strategy.
Alternative Options
Considered and Rejected: