Further to Minute No. 74 of the meeting of the Cabinet Member - Leisure and Tourism held on 6 January 2010, the Cabinet considered the report of the Leisure Director which provided an update on progress with the Master Plan for Crosby Coastal Park and to the procurement of the Phase 1 works.
This was a Key Decision and was included in the Council's Forward Plan of Key Decisions.
RESOLVED:
That approval be given to the increased provision of £26,879 in the capital programme, to be funded from Section 106 deposits, bringing the total scheme costs of the Phase 1 works for Crosby Coastal Park to £226,879.
The Cabinet Member considered the report of the Leisure Director updating on progress with the Master Plan for Crosby Coastal Park and seeking approval for the Phase 1 works; and indicating that a decision on this matter was required to enable progress on the Master Plan and the procurement of the proposed Phase 1 works.
This was a Key Decision and was included in the Council's Forward Plan of Key Decisions.
RESOLVED: That
(1) the work done to date be noted, and the first draft Crosby Coastal Park Master Plan be approved;
(2) the Leisure Director be authorised to seek competitive tenders for the Phase 1 landscape works;
(3) the Leisure Director be authorised to accept the lowest tenders for the works in accordance with delegated powers identified in the Council’s Constitution; and
(4) Cabinet be requested to include the additional sum of £26,879 from Section 106 deposits from Crosby Coastal Park in the Department’s Capital Programme.