Southport Cultural Centre

25/07/2012 - Southport Cultural Centre - Project Update

Further to Minute No. 68 of the meeting held on 8 December 2011, the Cabinet considered the report of the Strategic Director - Place which set out the history of the Southport Cultural Centre project, the potential additional cost and time overrun identified within the project: and the measures taken to mitigate this additional cost and time overrun.

 

RESOLVED:            That

 

(1)       the potential ‘worst case’ cost scenario now identified in respect of the completion of the project be noted; and

 

(2)       the Strategic Director - Place be requested to pursue all potential means of mitigating cost and time overruns, including;

 

            a.         where possible reducing specifications to the minimum acceptable level for a ‘fit for purpose’ facility;

 

            b.         undertaking any further possible Value Engineering exercises to maximise cost savings;

 

            c.         in conjunction with the Head of Corporate Finance and ICT, explore further funding arrangements to mitigate the increase in final project cost; and

 

            d.         in conjunction with the Head of Corporate Legal Services, explore the potential for minimising and/or recovering additional costs incurred.