The Cabinet considered the report of the Chief Executive and the Head of Corporate Finance and ICT which outlined the Council’s financial position for 2015/16 and 2016/17; set out the financial position in the context of the Council’s priorities; described the process undertaken to deliver a programme of savings options that reflected the need to produce a balanced budget alongside the objective of minimising the impact of the cuts on Sefton communities; provided the Cabinet with the first phase of savings options that would contribute to the forecast budget gap for the next two years; and outlined the gap remaining and the timetable for producing a balanced two year budget plan.

The Cabinet also considered a supplentary note which set out the following typographical errors in the report:

 

·         Page 67 - 34 Street Lighting Energy total actual budget is £1,447,400 not £1,180,000

 

·         Page 138 - 56 Commissioning Reduction of the Commissioning Service staffing – the text under Indicative Number of Staff at Riskshould read: up to 4 - 5 note that where changes and/or savings cannot be achieved through deletion of vacant posts, VR or VER then there may be a need for compulsory redundancies arising from this option.

 

The Chief Executive indicated that since 2011, the Council had faced unprecedented reductions in its resources as a result of cuts in Government Funding. In the preceding 4 years, cuts of £114 million had been identified and implemented and for the period 2015/16 to 2016/17, it was forecast that savings of a further £55 million would need to be identified. This represented a real term reduction of 45% on the 2011 spending level. She also indicated that the report set out some significant savings proposals totalling £30.288m which would have an impact on the delivery of services for the local community and further savings proposals of £24.418m had still to be identified. All of the savings proposals had been produced in accordance with the Core Principles and Budget Principles set out in the report in order to produce a two year budget plan and the proposals would need to be considered and approved by Members of the Council.

 

The Head of Corporate Finance and ICT indicated that the Overview and Scrutiny Management Board had considered and noted the content of the report at its meeting held on 25 November 2014 and requested that the following questions be submitted to the Cabinet for a response.

 

Budget Issue Proposal

Question / Response

 

Funding from Council Tax and Business Rates

 

Has the anticipated Council Tax income and business rates income been factored into the Council’s predicted income for the period 2015 to 2017 and beyond?

 

The Chief Executive responded that the projected income had been factored in to the report.

 

 

36 - Aiming High

 

 

Will respite provision still be provided?

 

The Director of Young People and Families responded that respite provision would still be provided but it would be at a significantly reduced level.

 

 

39 - Neighbourhoods and Partnerships

 

 

Will the co-ordination of the MARAC activities remain in-house and be undertaken by Council staff?

 

The Director of Corporate Services responded that it was anticipated that the activities would still be provided by in-house Council staff.

 

 

 

The Leader of the Council (Councillor P. Dowd) commented that the Council had faced unprecedented reductions in its resources as a result of cuts in Government Funding and that he felt that Sefton had been treated unreasonably by the Government in comparison with the much smaller budget reductions faced by Councils in the South of England and should be given more budgetary resources to deal with the demographics of the Borough. The Council would be faced with having to make some very difficult decisions as reasonably and as fairly as they can be made. He expressed thanks for the support of the public who appreciated that the Council was in the difficult position of having to make budget cuts forced upon it by the Government in order to set a balanced budget.

 

Decision Made:

 

That:

 

(1)     the approach to identifying options including  the Core Purpose as given in paragraph 2.2 and the Budget Principles as given in paragraph 4.2 of the report be endorsed;

 

(2)     it be noted that the potential budget shortfalls within the Medium Term Financial Plan as identified in December 2013 are:

 

         2015/16      £ 32.366m   

         2016/17      £ 22.340m

 

         Total           £ 54.706m

 

(3)    the work programme timetable set out in Annex A of the report be noted;

 

(4)    the budget process undertaken by officers to date as set out in paragraph 4 of the report and the process that officers would be undertaking to conclude the budget plan for the next two financial years be approved;

 

(5)    the items identified as efficiencies in Annex C1 of the report be approved and it be noted that these would be implemented immediately by officers;

 

(6)    it be noted that the details of the equality impact assessment information, the latest recorded position with respect to consultation, the identified risks and mitigating actions and information; and the impact on the community service users, partners and the Council for each of the proposals contained in Annex C2 of the report had been taken into account in the decision-making process; and officers be authorised to take necessary steps to progress the options pending consideration and decision by the Council in due course;

 

(7)    the Council be recommended to approve the following budget saving proposals as set out in Annex C2 of the report:

 

Most Vulnerable

Ref

Service Area

Change Proposal

2014/15

Budget

£000

Proposed Budget Reduction

£000

30

Children With Disability Service

Continue with the development of, and implement, new eligibility criteria

3,500

 

210

31

Domiciliary Care

Further explore the use of adaptations, equipment and Assistive Technology

 

Reduce the number of hours, number of calls, or number of carers utilised, where this is appropriate

 

Work in partnership with the voluntary/community sector to facilitate the development and utilisation of low-level alternative/preventative community services

 

Explore more outcome-focused commissioning

5,322

1,560

           Total                                                                                                                                                                                                                    

1,770

 

Core

Ref

Service Area

Change Proposal

2014/15

Budget

£000

Proposed Budget Reduction

£000

32

Street Cleansing

Further expand the use of electric vehicles and reduce the number of cleansing operatives delivering a manual service

3,670

 

360

33

Highways Infrastructure

 

To continue for a further 2 years the reduction of £800k which was introduced as an annual saving in previous years

6,672

 

800

Reduction in Highways Maintenance programmes  to focus on preventative, critical and high risk works

160

34

Street Lighting Energy

Invest to save in lighting columns and bulbs to allow reduced hours of lighting.

1,447

 

530

35

 

Libraries

Review of operation and management of libraries including bookfund and opening times

1,901

 

270

          Total                                                                                                                                     

2,120

 

Community Resilience

 

Ref

Service Area

Change Proposal

2014/15 Budget

£000

Proposed Budget Reduction

£000

36

Aiming High

Continue with the development of, and implement, new eligibility criteria

 

Review and potential cessation of funding for some activities

1,360

 

 

400

37

Housing Standards

Reduction in housing enforcement services including cessation of corporate illegal traveller sites co-ordination

450

 

60

38

Supported Living

Alternative and more efficient ways of meeting assessed care needs

18,435

 

1,200

39

Neighbourhoods

Reduction and re-prioritisation of activity

778

150

       Total

1,810

 

Economy & Environment

Ref

Service Area

Change Proposal

2014/15 Budget

£000

Proposed Budget Reduction

£000

40

Planning

Realign and reduce revenue budgets – including consultancy budgets

958

 

72

41

Planning

Increase in income across parts of the service Development Management, Building Control, and Technical Support [land charges] in light of economic forecast

 

130

42

Trading Standards

General reduction in enforcement activity. Limit resident service request response

480

 

 

55

43

EEMS (Energy and Environment)

 Reduction in Carbon reduction service and community energy service

384

 

84

44

Parks Maintenance

 

Botanic Gardens shop Closure

2,903

(Total Parks

 Maintenance

 Budget)

 

 

45

45

Increase allotment fees by an average of £10 per full size plot in 2016/17 and again in 2017/18.

Rates per full size plot will increase to £96 by 2017/18

20

46

The recharging of the cost of statutory checks to sports pavilions and repairs and maintenance of sports pavilions and associated hard infrastructure to sports users.

15

47

Further Changes in Style and Standards of Parks Management

144

48

Reduction in GM Contracts

60

49

Coast

Reduction to visitor and site management activities.

 

Extension to the length of the life guard contract on reduced terms.

 

Car-parking income charges

878

 

 

 

150

           Total

775

 

Health & Wellbeing

Ref

Service Area

Change Proposal

2014/15 Budget

£000

Proposed Budget Reduction

£000

50

Environmental Health

Reduction in front line environmental health regulatory services.

 

Reduction in pest control services but retain full rat control service

1,812

 

 

 

370

51

School Health

Re-specify/recommission the Healthy Child programme for the whole 0-19 age range

1,388

 

260

52

CHAMPS

Cessation of health protection/emergency preparedness and social marketing programmes and prioritising work

 

Ceasing Sefton’s contribution to cancer information service and CALM (mental health) service

220

 

 

 

 

57

53

Sports Leisure

Review and Restructure Management/Administration/

Operations including deletion of Service Manager post

 

Retender direct debit collection

Reduce agency payments

 

Energy efficiency              

1,044

 

 

 

 

470

 

       Total                                                                                                                                                                                                                  

1,157

 

Running the Council

Ref

Service Area

Change Proposal

2014/15 Budget

£000

Proposed Budget Reduction

£000

54

Adult Assessments

An end to end review of assessment and review policies, procedures and processes within Adult Social Care.  

7,580

 

 

300

55

Client Contribution

Restructuring and integrating the above service with the specialist Substance Misuse Housing and Welfare Rights Team

586

 

 

36

56

Commissioning

Reduction of the Commissioning Service staffing

Budget within Most Vulnerable

144

57

Attendance Welfare Service

Improved administration of legal procedures.

 

Reduced eligibility for service interventions.

 

Increase income

 

473

 

 

 

 

192

58

Youth Offending Team

Merge services and potential to reduce management capacity

661

 

120

59

Outreach Respite Recovery

Restructure the delivery team

635

 

96

60

Locality Assessment

Redesign of Common Assessment Framework team

 

Implement a stronger Lead Practitioner model

 

Implementation of electronic –common assessment framework (E-CAF)

 

299

 

132

61

School Standards and Effectiveness

Reduction in the Local Authority support provided to schools which are not in receipt of statutory intervention, requiring improvement or are assessed at risk of being less than good

530

 

 

 

60

62

Schools Regulatory Services

An end to end review of activity, policies, procedures and processes. 

449

 

60

63

14-19 Services

 Changes to commissioning arrangements for Information, Advice & Guidance

938

 

120

64

Children's administrative support

Service redesign

167

 

42

65

Highway management, development, design and safety.

Changes to charges

 

Service reorganisations

1,135

 

 

300

66

Parking

Review of service and charging regimes

-1,524

547

67

Property  Management

Closure and disposal of operational properties

1,052

60

68

FCERM (Flood and Coastal Erosion Risk Management)

Reduction in service,

 

Reduced response times

 

Reduction in works delivery

 

 

362

 

 

 

82

 

69

Regulatory Services Support

Reduction in administrative support  due to changes in working practices and increase to online services

219

 

24

70

Public Conveniences

Closure of all public conveniences

74

74

71

Bulky Items

Increasing collection charge from £7.50 to £10 per collection

48

48

72

Arts

Review management and opening times at the Atkinson

1,417

240

73

Sports Leisure- Active Sports

Increase in income due to increased charges and new programmes

0

 

36

74

Sports Leisure Aquatics

Maximise pool time at Meadows offering more swimming lessons to meet demand

-234

 

36

75

Public Health

Internal restructure to reflect the need to strengthen the influencing role of the team, and reduced need for commissioning capacity

822

 

 

278

76

Corporate Communications Team

Deletion of vacant posts and Team restructure

400

 

204

77

Transformation

Reduction of  Transformation resource

204

75

78

Legal Services

Restructure of the legal management department

 

Removal of the Monitoring Officer's budget.

914

 

 

134

79

 Finance & ICT Services

Restructuring Finance and ICT services after implementation of new financial system in 2015

 

Reduce ICT, printing and telephone costs in line with general Council reductions  

2,812

 

 

552

 

500

 

 

190

80

Learning & Development

Reduction in activity associated with learning and development

623

 

188

81

Personnel

Reduction in Personnel resource and efficiency savings

1,600

100

        Total                                                                                                                                                                                                                 

4,418

   TOTAL BUDGET REDUCTION

12,050

 

(8)    it be noted the officers would comply with Human Resource policies and procedures and this would include regular Human Resource monitoring reports to the Cabinet Member - Corporate Services and Performance.

 

(9)    it be noted that the figures in Annex C2 of the report are working assumptions of proposals to be considered by the Council and the figures should not be seen as predetermining any decisions;

 

(10)  it be noted that further options were being developed and assessed and a further report would be presented to Cabinet for consideration in January 2015; and

 

(11)  it be noted that the Cabinet and Council would be required to consider the coherence of the proposals when taken as a whole at the Council meeting to be held on 5 March 2015 in setting the 2015/16 budget and the two year financial plan.

 

Reasons for the Decision:

 

To ensure that the Cabinet was fully aware of the latest Medium Term Financial Plan position; to enable the consideration of £30.288m of savings options which would need to be phased over the two year budget plan and support the Council in its duty to agree a budget for 2015/16 and the level of 2015/16 Council Tax before the statutory date of 10 March 2015, and maintain a sustainable financial future for the Council by agreeing a balanced two year financial plan for 2015/16 and 2016/17.

 

Alternative Options Considered and Rejected:

 

Additional budget savings and options will need to be identified over the coming months to ensure that future years’ budgets can be balanced.  It is a legal requirement to set a balanced budget and to ensure the medium term financial position is robust.